The Environmental Protection Agency has instituted a new requirement for contractors who perform work on buildings constructed before 1978 to reduce exposure to lead paint. All contractors performing renovation, repair, and painting projects that disturb paint in homes, childcare facilities, and schools before built before 1978 must be certified in the new EPA Renovation, Repair, and Painting Rule (RRP) and follow specific work practices to reduce human exposure to lead paint by
Sound Transit accuses Japanese contractor Obayashi Corp. of leaving nine voids in the two-mile
To read the article click here
Moreland Corp. ("Moreland") contracted with the Department of Veterans Affairs ("V.A.") to design and construct a two-story medical clinic in
The Court of Federal Claims reviewed the default termination and found in favor of the contractor on its claim for the balance of the rent, plus interest. The court ruled that the default termination by the government was improper. It concluded the defects were largely cosmetic and easily could have been repaired if the V.A. had permitted Moreland to do so. It held that the building was safe to occupy during the repairs and the V.A.'s refusal to allow repairs breached the lease. Terming the government's conduct in its administration of the lease as "deplorable by any measure," the court held that even if the contractor had been in technical default, the V.A.'s bad faith compels the court to overturn the termination for default." The court invited Moreland to apply for attorneys' fees under the Equal Access to Justice Act. The V.A. breached it covenant of good faith and fair dealing – implied into every contract, including Government contracts." The court found two instances of bad faith by the V.A., the first was when the Contracting Officer denied two claims for added labor costs during construction, even though he believed they were meritorious and was prepared to grant nearly $300,000 in changes for them. The Contracting Officer denied the claims on advice of the V.A.'s legal counsel, "so the agency would have greater leverage in negotiating other claims."
Noting that government contractors are required to submit accurate and complete claims, the court held that the government has a reciprocal obligation to act in good faith. The court held that the outright denial of meritorious claims to obtain bargaining advantage over a contractor "will not be condoned by this Court" The second act of bad faith related to the V.A's need to install an auxiliary HVAC system on the roof, not part of the contract specifications. The V.A. demanded that Moreland conduct a structural loading study at no cost to the V.A. and justified its request with a two page report in which a V.A. engineer claimed there were many structural deficiencies in the building. Moreland declined to perform the study after consulting with the project's architect and engineer.
Finally, the court found that the V.A. report was used as a pretext to shift the cost of the structural study to Moreland and gave no credence to it because of the V.A.'s ulterior motive in having it prepared. The court awarded Moreland $17,673,850, plus interest and $438,188 in attorneys' fees under the Equal Access to Justice Act.
Moreland Corp. v.
The U.S. Citizenship and Immigration Services (USCIS) announced that the Office of Management and Budget has extended its approval of Form I-9 (Employment Eligibility Verification) to
Employers may use the Form I-9 with the revision date of either
The U.S. District Court for the District of Maryland upheld the legality of a federal regulation that will require many federal government contractors to use the E-Verify system to verify the employment eligibility of new hires, as well as certain existing employees. The regulation requires a new E-Verify clause to be included in certain federal contracts awarded or solicited on or after
Bell involved a construction contract under which the government issued an extensive series of change orders. Following the first of those change orders, the parties executed Modification 93, which stated in part the increased contract amount set forth in the Modification represented "full and equitable adjustment for the remaining direct and indirect costs of the [changed work] . . . and full and equitable adjustment for all delays resulting from any and all Government changes transmitted to the Contractor on or before August 31, 2000." Modification 93 also included the following "release" language: "the Modification agreed to herein is a fair and equitable adjustment for the Contractor's direct and indirect costs. This Modification provides full compensation for the changed work, including both Contract costs and Contract time. The Contractor hereby releases the Government, including all liability under the Contract for further equitable adjustment attributable to the Modification."
The interest in bidding on federal work, considering the new American Recovery and Reinvestment Act (Stimulus Bill) has attracted many new bidders to federal procurements. Federal contractors need to take note of the recent Business and Ethics compliance provisions of the Federal Acquisition Regulations. Any contractor receiving a government contract in excess of $5 million with a duration of 120 or more days shall:
Every contractor (except for small business) must establish a business ethics and awareness program and an internal control system within 90 days of contract award. The contractor's system and program shall include:
In addition, the contractor must verify subcontractor and supplier compliance. The Associated General Contractor's (AGC) Federal Government Contractor Ethics And Compliance Programs, tool kit and guidance publication includes generic ethics and compliance programs. This sample program assists contractors to navigate these complex and new regulatory waters.
In an unpublished opinion, the Division II Court of Appeals ruled this month that union managed employee benefit trust funds could not recover against a general contractor's payment bond and against an owner's retained percentage for unpaid trust fund contributions. In Leo Finnegan Construction Company v. Northwest Plumbing and Pipefitting Industry, a number of union managed employee benefit trust funds ("Trusts") filed lien notices against the general contractor's, Finnegan, performance bond and retainage held by the City of Tacoma on the Tacoma Police Department project. Finnegan had subcontracted with Chapman Mechanical. Chapman was required under a collective bargaining agreement between it and the Plumbers and Pipefitters Local 26 to pay monthly employee benefit contributions to the Trusts. Chapman failed to pay the required contributions and the Trusts recorded liens against the payment bond and retainage.
Further to the June 18, 2008 post, GAO Sustains Boeing Bid Protest of Massive Air Force Contract, the United States Government Accountability Office has released the full, redacted, decision on the Boeing protest, which can be found here.
While this was certainly the World Series of bid protests, as noted in the previous posting, the process undertaken by Boeing and its team of attorneys is the same required by construction contractors in their protests of most federal procurements.
This case (Matia Contractors, Inc. v. City of Bellingham, Court of Appeals, Div I) addressed the question of whether a general contractor who is filing a lawsuit against a public entity for breach of contract is required to give notice to the public entity prior to filing its lawsuit. Matia was the general contractor on the Joe Martin Field project, Bellingham's municipal baseball stadium. Bellingham terminated Matia's contract and Matia sued.
Bellingham argued that Matia's lawsuit was barred because Matia did not notify the City before it filed its lawsuit as required by a City ordinance and state statute. Cities can enact ordinances providing for claim filing requirements but they cannot be more restrictive than the authorizing state statute. The authorizing state statute, RCW 4.96.010, provides that the pre-lawsuit claim filing requirements apply only to tort claims (i.e. personal injury, negligence, etc.). Therefore, because Matia's claim was for breach of contract, and not tort, it was not required to comply with the pre-lawsuit claim filing requirements of the City and the state statute.
Although the Division One Court of Appeals' ruling in this case may seem self apparent, the Division Three Court of Appeals reached the opposite result in a case decided in 2004.
In government contracting, claim preparation costs (attorneys' fees and consultant costs) are generally not recoverable by the contractor when pursuing a claim. On the other hand, if consultant costs are incurred in preparing a "request for equitable adjustment," the consultant costs and attorneys' fees may be recoverable. It depends on the somewhat nebulous distinction between an administrative cost and a cost incurred incident to prosecution of a contract claim. As long as the consulting costs and attorneys' fees are incurred in the preparing of a request for equitable adjustment, for the purpose of seeking a negotiated resolution of pending issues, the costs are allowable. If the contractors' "genuine purpose" in incurring the costs was to further the negotiation process, it is a contract administrative cost allowable under FAR 31.205‑33. On the other hand, however, if the underlying purpose was to promote the prosecution of a Contract Disputes Act (CDA) claim, the costs are not allowable. Under FAR 31.205‑33(b), the cost of legal and consulting services are generally allowable "when reasonable in relation to the service rendered." "A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business." FAR 31.201‑3.