Construction Law Blog

Blog Disclaimer: The content provided on this website is for informational purposes only and is not legal advice. Transmission of this information is not intended to create, and receipt does not constitute, an attorney-client relationship. The information provided is intended for general information which may or may not reflect the most current developments. Read More

- OR -

Subcontractor Allowed to Sue Designer for Negligence: California Courts Chip Away at the Economic Loss Doctrine (Independent Duty Rule)

Date: August 23, 2017  /  Author: John P. Ahlers  /  Categories: Government Contracts, Contracting, Indemnity, Delay Claims, Damages, Construction Defect, Claims  /  Comments (0)

An architect may have to pay over $1 million to a subcontractor who was contractually obligated to rely on the designer’s plans – even though the architect was not a party to the contract.  That was the ruling in U.S. f/u/b/o Penn Air Control, Inc. v. Bilbro Constr. Co., Inc. The dispute involved a $7.3 million design-build contract award to Bilbro Construction (“Bilbro”) to renovate a facility for the Naval Facilities Engineering Command in Monterey, California. 

Bilbro hired an architect (“FPBA”) to serve as the designer of record and provide all the architectural design services.  FPBA’s design team included an acoustical sub-consultant (Sparling).  The general contractor (design builder) also retained Alpha Mechanical (Alpha) as the mechanical electrical and plumbing (“MEP”) design/build subcontractor.

Court of Appeals Discusses Implied Duty of Good Faith and Fair Dealing in Public Works Contracting

Date: August 16, 2017  /  Author: Lindsay K. Taft  /  Categories: Government Contracts, Contracting, Regulatory Administration, Construction News and Notes, Liens/Bond Claims, Delay Claims, Damages, Claims, Change Orders  /  Comments (0)

The implied duty of good faith and fair dealing is implied in every contract, including construction contracts.  Generally speaking, this implied duty requires parties cooperate with one another so that they each obtain the full benefit of their contracted bargain.  Recently, the Court of Appeals (Division II) in Nova Contracting, Inc. v. City of Olympia discussed this duty’s application to a public works contract.

In early 2014, the City of Olympia published an invitation for bids to replace a culvert that conveyed a creek underneath a paved bike trail.  Nova Contracting was awarded the Project.  The specifications required that Nova submit a number of submittals, the approval of which was required before Nova could commence work.  The contract also provided that the City’s decision with respect to these submittals would be final and that Nova would bear all risk and costs of delays caused by non-approval of any submittals.

Subcontractors on Washington Public Projects Can Now Get Their Retainage Money Sooner

Date: July 20, 2017  /  Author: Brett M. Hill  /  Categories: Out of the Ordinary, Government Contracts, Contracting, Construction News and Notes, Memorable Quotes, Rants and Raves, Recent Legislation, Claims  /  Keywords: SUBCONTRACTORS ON WASHINGTON PUBLIC PROJECTS CAN NOW GET THEIR RETAINAGE MONEY SOONER 1  /  Comments (0)

Subcontractors on public projects in Washington State will no longer be required to wait until final acceptance of the project to get their retainage money. A new statute, which goes into effect on July 23, 2017 and applies only to Washington public projects, will allow subcontractors to get their retainage sooner.

Under prior law, a subcontractor could only get its retainage prior to final acceptance if the general contractor provided a retainage bond to the public owner to secure a release of the general contractor’s retainage and the subcontractor then provided a similar retainage bond to the general contractor in the amount of its own retainage. If the general contractor decided to not provide a retainage bond to the owner, the subcontractor would be forced to wait until final acceptance of the project before it could get paid its retainage.

Washington Contractors Should Refrain from Separately Itemizing and Billing Customers for B&O Tax

Date: June 14, 2017  /  Author: Bruce A. Cohen  /  Categories: Change Orders, Claims, Rants and Raves, Memorable Quotes, Construction News and Notes, Contracting, Out of the Ordinary  /  Keywords: Washington Contractors Should Refrain from Separately Itemizing and Billing Customers for B&O Tax 2  /  Comments (0)

Construction attorneys rarely encounter state and local tax issues.  However, in a recent negotiation over a disputed change proposal, an Owner’s attorney argued that Washington prohibits recovery of B&O tax as a separately-billed line item in the change proposal.  Given that itemization of B&O surcharges seemed a fairly common business practice, I was initially skeptical of the position.  Upon further review, it became apparent that the Owner’s argument was indeed correct and that many contractors may be unknowingly violating the law by separately itemizing and adding a percentage for B&O tax to their billings or change proposals.

WSDOT Excludes Non-Minority Women-Owned DBEs from Participation Goals

Date: June 2, 2017  /  Author: Ellie Perka  /  Categories: Recent Legislation, Rants and Raves, Memorable Quotes, Construction News and Notes, Contracting, Construction Bidding, Government Contracts, Out of the Ordinary, MBE/DBE/WBE  /  Keywords: WSDOT Excludes Non-Minority Women-Owned DBEs from Participation Goals 3  /  Comments (0)

A drastic change has been implemented by the Washington State Department of Transportation (“WSDOT”) to the Disadvantaged Business Enterprise (“DBE”) Program in Washington.  Effective June 1, 2017, WSDOT has implemented a “waiver” to exclude women-owned DBEs[i] from qualifying toward Condition of Award (“COA”) Goals on federally-funded projects.  This move is significant.  It will likely result in long-lasting detrimental impacts on the DBE community, women-owned businesses, and the entire construction community in Washington.  The construction industry should be in an uproar over this change.  Instead, it has largely gone unnoticed (likely because its impacts have not yet been felt).  It is a de facto exclusion of women-owned businesses from the DBE program, and the severity of this change cannot be overstated. 

General Construction v. Grant County PUD: Chalkboard Notice is Invalid and Engineer Cannot Waive Notice Requirements

Date: May 30, 2017  /  Author: Brett M. Hill  /  Categories: Change Orders, Claims, Damages, Rants and Raves, Memorable Quotes, Construction News and Notes, Contracting, Notice Issues  /  Keywords: General Construction v. Grant County PUD: Chalkboard Notice is Invalid and Engineer Cannot Waive Notice Requirements 4  /  Comments (0)

 

I previously posted a blog about the General Construction v. Grant County PUD case and the Court of Appeals’ rulings regarding notice and claim procedures.[i]  The General Construction case is also noteworthy for two other issues that were raised in that case.[ii]  The first issue involved whether a contractual written notice requirement is satisfied when the notice is provided on a chalkboard only.  The second noteworthy issue is whether the Public Utility District’s (“PUD”) own in-house engineer could waive the contractual notice and claim procedures in the PUD’s contract.

General Construction v. Grant County PUD: Courts Continue to Struggle with Mike M. Johnson Case

Date: May 24, 2017  /  Author: Brett M. Hill  /  Categories: Notice Issues, Contracting, Construction News and Notes, Memorable Quotes, Rants and Raves, Delay Claims, Claims, Change Orders  /  Keywords: General Construction v. Grant County PUD: Courts Continue to Struggle with Mike M. Johnson Case 5  /  Comments (0)

Another court in Washington was asked to apply the Mike M. Johnson[i] decision to a contractor’s claim for extra work.  This time it was the Division III Court of Appeals in Washington.  The Division III Court of Appeals, which covers all of Eastern Washington, had a hand in the original Mike M. Johnson case.  That court is the intermediary court that ruled in favor of the contractor in Mike M. Johnson.  It held that there were issues of fact as to whether Spokane County, in the Mike M. Johnson case, had actual notice of the changed conditions and, thus, waived the notice and claim procedures that the County was attempting to rely upon.  The Division III Court of Appeals was later overruled by the Washington State Supreme Court, which held as a matter of law that the County of Spokane had not waived the notice and claim procedures.  This time around, the Division III Court of Appeals, for the most part, ruled in favor of the public entity and followed the Mike M. Johnson decision.

Is Reversing an Arbitration Award Going to Become Easier in the Future?

Date: May 10, 2017  /  Author: John P. Ahlers  /  Categories: Alternative Dispute Resolution (ADR), Contracting, Construction News and Notes, Rants and Raves, Claims  /  Keywords: Is Reversing an Arbitration Award Going to Become Easier in the Future? 6  /  Comments (0)

Generally, contractors choose arbitration because it is a cost-effective method of dispute resolution, and primarily because an award issued in arbitration is final.  Vacating an arbitration award is only permitted on very narrow grounds.  A party must demonstrate that the award was procured by corruption, fraud, or undue means, or that an arbitrator exceeded his/her power (very high burdens).  Arbitration rules in other states are similar to the Washington statute.  Stated simply, it is very difficult to reverse an arbitration award—or is it?  These two cases do not indicate a trend but do remind us that an arbitrator’s power is limited to that power granted to him/her by contract.

ASBCA Validates New Type of Claim Related to Unfavorable CPARS Review

Date: April 27, 2017  /  Author: John P. Ahlers  /  Categories: Government Contracts, Contracting, Construction News and Notes, Memorable Quotes, Rants and Raves, Claims  /  Comments (0)

For government contractors, an unfavorable performance rating review posted to the Contractor Performance Assessment Reporting System (“CPARS”) can be extremely costly.  Many of the government-negotiated solicitations include past performance as an important, and sometimes even primary, evaluation factor for contract award.  An unfavorable CPARS review on a past contract can cause the contractor to incur substantial extra costs in addressing the unfavorable review with contracting officers on future solicitations, and, in some instances, the contractor saddled with an unfair or inaccurate CPARS may have to challenge the review and recover some of these costs.

Blog: Congress Strikes a Blow to President Obama’s “Fair Pay and Safe Workplaces” Executive Order 13673

Date: March 20, 2017  /  Author: John P. Ahlers  /  Categories: Out of the Ordinary, Government Contracts, Construction Bidding, Contracting, Construction News and Notes, Memorable Quotes, Rants and Raves, Recent Legislation, Employment  /  Keywords: Blog: Congress Strikes a Blow to President Obama’s “Fair Pay and Safe Workplaces” Executive Order 13673 7  /  Comments (0)

On October 25, 2016, the Federal Acquisition Regulatory Council (FAR Council) and the U.S. Department of Labor implemented former President Obama’s Executive Order 13673: “Fair Pay and Safe Workplaces” rules.  The rules became effective on October 25, 2016 and fundamentally altered the way federal contractors and subcontractors will need to handle and resolve employment and labor claims, as well as compliance issues involving their entire workforce.  The final rules can also result in otherwise-capable companies being “blacklisted” and effectively barred from federal contracts and subcontracts based on labor and employment law violations related or unrelated to prior or current federal contract performance.  The centerpiece of the new regulatory scheme was the new disclosure and responsibility requirements.  Contractors and subcontractors needed to disclose all “labor law decisions” that they had during the three years (prior to bid submission) as part of the process of applying for a new federal contract or subcontract.  If a contractor or subcontractor has too many “labor law decisions” to report or the few it has are too severe, pervasive, repeated, or willful in the eyes of the government “experts,” the company could be deemed “non-responsible” and denied a contract.